This is Local 213’s work information for Monday, September 29th, 2025. 

The hall will be closed Tuesday, September 30th for the holiday and will re-open Wednesday morning at 8:00am.

1st call is for Lorneville at the Irving Pulp and Paper Mill: They require

  *1 F3/F4 Welders to test on Duplex Tig and Carbon Stick.

Starting ASAP, at 7:00am. Duration is 3 weeks plus. Will be working 4×10’s Monday – Thursday. 7am-5pm. This work is under the industrial agreement. Must be clean-shaven and fit-tested. Must be able to climb and work from heights. Must have all safety training up to date.  

2nd call is for Cam at the Irving Oil Refinery: They require

*1 Journeyman Pipefitter * 1 F3/F4 Welder to test on F3/F4 F6/F5

Starting ASAP, at 7:00am. Duration is unknown. Will be working 4×10’s Monday – Thursday. The job scope is maintenance. This work is under the GPMA Agreement under short-term conditions. Must be clean-shaven and fit-tested. Must be able to climb and work from heights. Must have all safety training up to date, and a D&A test is required. 

3rd  call is for Stuart Olson at the Irving Oil Refinery: They require

*1 Journeyman Pipefitters 

Starting ASAP at 7:30pm. Night Shift . Duration is 2 weeks plus. Will be working 6×10’s. This is a shutdown call.  This work is under the GPMA Agreement under short-term conditions. Must be clean-shaven and fit-tested. Must be able to climb and work from heights. Must have all safety training up to date, and a D&A test is required. 

Any local members interested in these calls, please contact the hall Wednesday morning between 8 and 10am.

Thank you, and have a Great Evening!